Notice: wpdb::prepare was called incorrectly. The query does not contain the correct number of placeholders (1) for the number of arguments passed (2). Please see Debugging in WordPress for more information. (This message was added in version 4.8.3.) in C:\inetpub\wwwroot\websites\gc3builders.com\wp-includes\functions.php on line 4139

Notice: wpdb::prepare was called incorrectly. The query does not contain the correct number of placeholders (1) for the number of arguments passed (2). Please see Debugging in WordPress for more information. (This message was added in version 4.8.3.) in C:\inetpub\wwwroot\websites\gc3builders.com\wp-includes\functions.php on line 4139

Levels of Gypsum Drywall Finish

November 21, 2017Interiors and Finishes

The finished appearance of drywall largely depends on the quality of framing and care exercised in applying the drywall panels. The better the framing and cladding, the easier it is to achieve a near-perfect wall. The last remaining challenge is to finish the joints to meet visual appearance expectations.

Contract documents traditionally use nonspecific terms such as “industry standards” or “workmanlike finish” to describe how finished gypsum board walls and ceilings should look. This practice has often led to confusion about the degree or level of finishing required for a particular job.

Five leading industry trade associations — the Association of the Wall and Ceiling Industries International (AWCI), Ceilings and Interior Systems Construction Association (CISCA), Gypsum Association (GA), Drywall Finishing Council (DWFC) and Painting and Decorating Contractors of America (PDCA) — have combined efforts to collectively adopt a set of industry-wide recommended specifications for levels of gypsum board finish. This specification identifies five levels of finishing.

Level 0: Level 0 is used in temporary construction or wherever the final decoration has not been determined. No taping, finishing or corner beads are required.

Level 1: Frequently used in plenum areas above ceilings, in attics, in areas where the assembly would generally be concealed, or in building service corridors and other areas not normally open to public view. Some degree of sound and smoke control is provided; in some geographic areas, this level is referred to as “fire-taping,” although this level of finish does not typically meet fire-resistant assembly requirements. Where a fire resistance rating is required for the gypsum board assembly, details of construction should be in accordance with reports of fire tests of assemblies that have met the requirements of the fire rating imposed.

All joints and interior angles shall have tape embedded in joint compound. Accessories are optional at specifier discretion in corridors and other areas with pedestrian traffic. Tape and fastener heads need not be covered with joint compound. Surface shall be free of excess joint compound. Tool marks and ridges are acceptable.

Level 2: It may be specified for standard gypsum board surfaces in garages, warehouse storage, or other similar areas where surface appearance is not of primary importance.

All joints and interior angles shall have tape embedded in joint compound and shall be immediately wiped with a joint knife or trowel, leaving a thin coating of joint compound over all joints and interior angles. Fastener heads and accessories shall be covered with a coat of joint compound. Surface shall be free of excess joint compound. Tool marks and ridges are acceptable.

Level 3: Typically used in areas that are to receive heavy texture (spray or hand applied) finishes before final painting, or where commercial- grade (heavy duty) wall coverings are to be applied as the final decoration. This level of finish should not be used where smooth painted surfaces or where lighter weight wall coverings are specified. The prepared surface shall be coated with a drywall primer prior to the application of final finishes.

All joints and interior angles shall have tape embedded in joint compound and shall be immediately wiped with a joint knife or trowel, leaving a thin coating of joint compound over all joints and interior angles. One additional coat of joint compound shall be applied over all joints and interior angles. Fastener heads and accessories shall be covered with two separate coats of joint compound. All joint compounds shall be smooth and free of tool marks and ridges. The prepared surface shall be covered with a drywall primer prior to the application of the final decoration.

Level 4: This level should be used where residential grade (light duty) wall coverings, flat paints, or light textures are to be applied. The prepared surface shall be coated with a drywall primer prior to the application of final finishes. Release agents for wall coverings are specifically formulated to minimize damage if coverings are subsequently removed.

The weight, texture, and sheen level of the wall covering material selected should be taken into consideration when specifying wall coverings over this level of drywall treatment. Joints and fasteners must be sufficiently concealed if the wall covering material is lightweight, contains limited pattern, has a glossy finish, or has any combination of these features. In critical lighting areas, flat paints applied over light textures tend to reduce joint photographing. Gloss, semi-gloss, and enamel paints are not recommended over this level of finish.

All joints and interior angles shall have tape embedded in joint compound and shall be immediately wiped with a joint knife or trowel, leaving a thin coating of joint compound over all joints and interior angles. In addition, two separate coats of joint compound shall be applied over all flat joints and one separate coat of joint compound applied over interior angles. Fastener heads and accessories shall be covered with three separate coats of joint compound. All joint compounds shall be smooth and free of tool marks and ridges. The prepared surface shall be covered with a drywall primer like Sheetrock First Coat prior to the application of the final decoration.

Level 5: The highest quality finish is the most effective method to provide a uniform surface and minimize the possibility of joint photographing and of fasteners showing through the final decoration. This level of finish is required where gloss, semi-gloss, or enamel is specified; when flat joints are specified over an untextured surface; or where critical lighting conditions occur. The prepared surface shall be coated with a drywall primer prior to the application of final decoration.

All joints and interior angles shall have tape embedded in joint compound and be immediately wiped with a joint knife or trowel, leaving a thin coating of joint compound over all joints and interior angles. Two separate coats of joint compound shall be applied over all flat joints and one separate coat of joint compound applied over interior angles. Fastener heads and accessories shall be covered with three separate coats of joint compound.

A thin skim coat of joint compound shall be trowel applied to the entire surface. Excess compound is immediately toweled off, leaving a film or skim coating of compound completely covering the paper. The surface must be smooth and free of tool marks and ridges. The prepared surface shall be covered with a drywall primer prior to the application of the final decoration.